- The Tube Tech Team faced an unusual challenge in having to clean each half of the condenser while the other half remained on-line at operating temperature, so that some power generation could be maintained.
- This was preferred by the National Grid, as it avoids having to re-synchronise the plant's output when it comes back online.
- Over 300Kg of scale and river silt deposit were flushed out of the condenser tubes, while the plastic packings were removed without difficulty, thanks to the special darTT that Tube Tech fired down each tube to clean and clear them.